Federal regulators give more time to complete gas pipeline extension in Virginia, North Carolina
View
Date:2025-04-14 11:03:25
RALEIGH, N.C. (AP) — The builders of a proposed natural gas pipeline that will enter North Carolina from Virginia now have another 2 1/2 years to complete the project after federal regulators pushed back a deadline for the work.
The Federal Energy Regulatory Commission approved on Tuesday a request by owners of the proposed 75-mile (121-kilometer) Southgate extension of the Mountain Valley Pipeline to allow for more time for construction, news outlets reported.
According to the previous FERC certificate, the project was supposed to be built and in service six months ago. But permitting problems in North Carolina and Virginia amid legal challenges to the larger Mountain Valley Pipeline meant the owners missed the deadline.
Now, with the FERC’s order, the owners have until June 2026 to complete the MVP Southgate project and bring it into service. More permits still must be secured for construction to occur.
The owners of the project, which includes a consortium of natural gas and energy companies, are pleased with FERC’s decision, project spokesman Shawn Day said.
“At the appropriate time, Mountain Valley intends to pursue all necessary permits and authorizations to complete construction of the MVP Southgate project,” Day wrote in an email.
The Southgate extension will continue pushing gas south from the planned 303-mile (488-kilometer) Mountain Valley Pipeline that will go through West Virginia and Virginia. The extension would run from the main pipeline in Pittsylvania County, Virginia, into Rockingham and Alamance counties in North Carolina.
The future of the pipeline — and thus the extension — appeared uncertain with opposition from environmental groups and some elected officials. But Congress last year essentially ordered the pipeline’s construction as part of the bipartisan bill to increase the debt ceiling. This past summer, federal courts also dismissed a challenge to construction permits for the Mountain Valley Pipeline and allowed construction to resume.
MVP Southgate would be the second pipeline carrying natural gas to enter North Carolina. Project supporters have said additional gas capacity is needed for reliable and affordable energy. Duke Energy also appears to need a supply to shift its coal-fired power plants to natural gas.
Democratic Gov. Roy Cooper and other elected Democratic officials — including U.S. Reps. Kathy Manning and Valerie Foushee of North Carolina and Reps. Jennifer McClellan and Bobby Scott of Virginia — opposed giving more time for the project. The members of Congress sent a letter Monday to FERC expressing concerns about the extension’s impact on the safety of residents and the environment as efforts to move away from fossil fuels continue.
Still, MVP Southgate needs permits from federal and state agencies, such as the U.S. Army Corps of Engineers and the North Carolina Department of Environmental Quality.
Also Tuesday, FERC agreed to a request from the Mountain Valley Pipeline owners to charge higher rates for the gas being shipped through the buried pipeline. The transportation rate is paid by companies that deliver the gas to end users.
The estimated cost of the pipeline is now $7.2 billion, compared to the first projection of $3.7 billion.
veryGood! (959)
Related
- Bodycam footage shows high
- Last Day To Get 70% Off Amazon Deals: Earbuds, Smart Watches, Air Mattresses, Cowboy Boots, and More
- Women's March Madness games today: Schedule, how to watch Monday's NCAA Tournament
- Linda L. Bean, entrepreneur and granddaughter of L.L. Bean founder, dies at 82
- The city of Chicago is ordered to pay nearly $80M for a police chase that killed a 10
- Families in Massachusetts overflow shelters will have to document efforts to find a path out
- What are the 10 largest US lottery jackpots ever won?
- Off the Grid: Sally breaks down USA TODAY's daily crossword puzzle, Jump Start
- Working Well: When holidays present rude customers, taking breaks and the high road preserve peace
- Women's March Madness games today: Schedule, how to watch Monday's NCAA Tournament
Ranking
- Trump's 'stop
- Major cities are running out of water. A new World Water Day report says it could worsen global conflict.
- Supreme Court again confronts the issue of abortion, this time over access to widely used medication
- Full transcript of Face the Nation, March 24, 2024
- Meta donates $1 million to Trump’s inauguration fund
- Boeing CEO Dave Calhoun to step down by end of year
- Academics challenge Florida law restricting research exchanges from prohibited countries like China
- Teen was driving 112 mph before crash that killed woman, 3 children in Washington state
Recommendation
Romantasy reigns on spicy BookTok: Recommendations from the internet’s favorite genre
It's National Puppy Day! Are you ready to be a dog owner? What to know about puppies
Katie Couric Is a Grandma as Daughter Ellie Welcomes First Baby
Snowstorm unleashes blizzard conditions across Plains, Midwest
Average rate on 30
Kamala Harris will meet Guatemalan leader Arévalo on immigration and his anti-corruption drive
LSU uses second-half surge to rout Middle Tennessee, reach women's Sweet 16
Jennifer Lopez is getting relentlessly mocked for her documentary. Why you can't look away.